Primavera P6 XER export

An automated schedule is only useful if it lands inside the tool the project actually runs on. Sensali finishes its pipeline by writing a Primavera P6 XER file rather than handing back a document a planner has to retype.

Short answer

XER is Oracle Primavera P6's native exchange format. A Sensali export contains the construction activities, the predecessor and successor relationships between them with relationship type and lag, and the resource and crew assignments derived from project staffing data. The file imports directly into P6, so the generated network can be scheduled, resource levelled and baselined like any other schedule.

Last updated 20 August 2026 / Sensali, Perth, Western Australia

What an XER file is

XER is the exchange format Primavera P6 uses to move a project between databases. Unlike a spreadsheet it carries the full structure of a schedule: activities, calendars, relationships, resources and assignments. If a tool cannot write XER, its output has to be rebuilt by hand inside P6, which removes most of the time saved.

What is inside a generated export

ElementSourceDetail
ActivitiesSequenced item groupsConstruction activities per unit and per process area
RelationshipsConstruction methodologyPredecessor and successor links, finish to start with lag where required
DurationsProject engineering dataDerived from calculated hours rather than assumed
ResourcesProject staffing dataCrew sizes assigned at a 1:1 basis to the project's own data
Codes and structureProcess area assignmentActivities grouped by the physical area they belong to

On the models processed so far the pipeline has generated 220 construction activities and 190 predecessor and successor relationships, from 264,101.9 engineering hours calculated out of the models.

Importing into P6

  • Import the XER into Primavera P6 as a new project, or into an existing EPS node.
  • Schedule the project so P6 calculates dates from the imported relationship network.
  • Review the activity network by process area; gating means bulk work in an area follows the equipment in that area.
  • Adjust calendars and resource curves to project standards, then baseline.

Planners keep full control. The generated schedule is a starting network built from the model and the methodology, not a locked black box output.

Why not a spreadsheet

Spreadsheet output loses relationships. A list of activities with durations still leaves the hardest part of planning, the dependency network, to be recreated manually. Writing XER means the logic survives the handover.

Upstream of the export

The export is the last of five stages. See Navisworks to Primavera P6 for the full pipeline and construction sequencing automation for the logic that builds the network.

Run this on one of your completed projects

We are working with a small number of EPC and project controls teams to validate Sensali. NDA available before any model or project data is shared.